HYDROCARBON PRODUCTION SYSTEM, METHOD FOR PERFORMING CLEAN-UP AND METHOD
FOR CONTROLLING FLOW
Abstract
The present invention relates to a device for transmitting fluid from a
subsea producing module (8) to a subsea receiving module (9) comprising a
choke valve (3) in a main flowpath (7) of the fluid. A bypass line (2) is
arranged in parallel to the choke valve (3) and the bypass line (2) is
connected to the main flowpath (7) by a bypass connection (1).
| Inventors: |
Selstad; Stian; (Spikkestad, NO)
|
| Serial No.:
|
003795 |
| Series Code:
|
13
|
| Filed:
|
August 7, 2009 |
| PCT Filed:
|
August 7, 2009 |
| PCT NO:
|
PCT/NO2009/000278 |
| 371 Date:
|
January 12, 2011 |
| Current U.S. Class: |
166/344; 166/319; 166/368 |
| Class at Publication: |
166/344; 166/319; 166/368 |
| International Class: |
E21B 34/04 20060101 E21B034/04; E21B 34/00 20060101 E21B034/00; E21B 33/035 20060101 E21B033/035 |
Foreign Application Data
| Date | Code | Application Number |
| Aug 7, 2008 | NO | 20083451 |
Claims
1. A hydrocarbon production system, comprising: a subsea production
module operatively connected to a subsea well; a subsea receiving module;
a main flow path including a subsea production choke valve fluidly
connecting the subsea production module and the subsea receiving module;
and wherein a bypass line is arranged parallel to the subsea production
choke valve and is connected to the main flow path by a bypass connection
to conduct production fluid around the subsea production choke valve.
2. The system according to claim 1, wherein the bypass connection
comprises at least one valve capable of opening and closing access from
the main flow path to the bypass connection.
3. The system according to claim 2, wherein the at least one valve is a
two-way valve comprising a first position to open access to the subsea
production choke valve and closing access to the bypass connection and a
second position to open access to the bypass connection and close access
to the subsea production choke valve.
4. The system according to claim 2, wherein the at least one valve is a
three-way valve comprising a first position to open access to the subsea
production choke valve and closing access to the bypass connection, a
second position to open access to the bypass connection and close access
to the subsea production choke valve, and a third position to close
access to both the subsea production choke valve and the bypass
connection.
5. The system according to claim 2, wherein the at least one valve is a
four-way valve comprising a first position to open access to the subsea
production choke valve and closing access to the bypass connection, a
second position to open access to the bypass connection and close access
to the subsea production choke valve, a third position to close access to
both the subsea production choke valve and the bypass connection, and a
fourth position to open access to both the subsea production choke valve
and the bypass connection.
6. The system according to claim 1, wherein the bypass connection is
connected to the main flow path by two connections, one at either side of
the subsea production choke valve.
7. The system according to claim 1, wherein the subsea receiving module
is a manifold.
8. The system according to claim 1, wherein the subsea production
producing module is a Xmas Tree.
9. The system according to claim 1, wherein the bypass connection is
arranged to transmit fluid in both directions of the bypass line to
provide a flow path both for the production fluid and injection fluid.
10. The system according to claim 1, wherein the production fluid
entrains debris.
11. A method for performing clean-up of a subsea well and a subsea
production module in a hydrocarbon production system, the subsea
production module operable to produce a fluid transmitted through a main
flow path including a choke valve, wherein during clean-up, a bypass
connection is opened to direct at least one of the produced fluid and the
treatment fluid from the subsea well to a bypass around the choke valve
in order to prevent debris in the flow from damaging or blocking the
choke valve.
12. A system for controlling flow in a hydrocarbon production system
comprising: a subsea production module operatively connected to a subsea
well; a subsea receiving module; a main flow path including a subsea
production choke valve fluidly connecting the subsea production module
and the subsea receiving module; wherein during a situation with a
pressure in the well higher than the pressure necessary to deliver a
desired production flow rate, the subsea production choke valve is choked
to limit the flow rate to a desired flow rate; and wherein during a
situation when a flow rate is desired, which substantially corresponds to
a maximum delivery rate of the subsea well, a bypass line is opened to
direct the flow outside the subsea production choke valve.
Description
FIELD OF THE INVENTION
[0001] The present invention relates to a hydrocarbon production system
comprising a subsea well, a subsea production module, a subsea receiving
module and a choke valve situated in a main flow path of production fluid
from the well, between the production module and the receiving module.
BACKGROUND OF THE INVENTION AND PRIOR ART
[0002] In a subsea installation, several wells or Xmas Trees are connected
to a common manifold. The pressures in these wells are different, and to
be able to transmit oil or gas to the common manifold, the pressure needs
to be substantially equal. Thus, a choke valve is installed between each
Xmas Tree and the manifold to adjust and control the pressure.
[0003] It is a standard procedure to perform a clean-up process in a Xmas
Tree as a basis for commissioning. Traditionally, the clean-up is done
through the choke valve. The product of the clean-up can be fluids with
different viscosity, and it can also comprise different types and
dimensions of debris, e.g. sand, mud etc. This complex clean-up product
comprising debris provides a substantial risk of choke malfunction and
blockage when transported through the choke valve. There has been a
preference, or in some cases even a requirement, from the oil operators
that choke valves shall be designed to handle this clean-up process. On
the other hand, no existing choke valve vendor can or will give a
guarantee that the choke can tolerate this, as it is almost impossible to
know what type debris will flow through the choke and what dimension the
debris will have. Some choke valves might have a design which can protect
the internal parts from debris compared to other choke valves. But still
it will always be a risk for blockage of trim ports in the choke valve.
[0004] The requirements for the features of the choke valve are different
in the first phase of production of oil/gas than in the later phases of
production in the Xmas Tree. Due to the high pressure in the first phase
of production, good controllability of the choke valve is typically
desired in that phase. In the later phases of the production, the
pressure will decrease and the choke valve then needs to have features
that provide maximum flow. Both good controllability and maximum flow are
features required by the oil operators, but they are not sufficiently
present in any choke valves on the market today. Therefore the solution
has been to replace the choke valve with good controllability used in the
first phase with a different choke valve that provides maximum flow for
the later phases. This replacement procedure is a complex procedure that
involves use of e.g. an ROV (Remote Operated Vehicle) and it also
requires shutting down the installation during the replacement procedure.
[0005] It is known from WO 2006/041820 an operating pressure and waste
management apparatus for use during drilling operations. In this
apparatus one of two choke valves is used to maintain a pressure in the
system. Since the fluid flow out of the well is drilling mud, it will
contain a substantial amount of drill cuttings. These will have to pass
through the choke valve. As mentioned above there is today no choke
valves on the market that are able to handle such an amount of debris
without quickly becoming degraded, unless the pressure of the fluid and
the flow rate is very low. The drill mud will generally have very low
pressure and flow rates compared to production fluids.
[0006] WO 2006/041820 describes a diverter line that may divert the drill
mud flow outside of the two choke valves in the unlikely event that they
both should fail. The arrangement of WO 2006/041820 would, however, not
be considered used in a subsea production system, as the flow rates and
the pressure is usually much higher in such a production system.
SUMMARY OF THE INVENTION
[0007] It is therefore a need for a solution that provides a remedy to the
above mentioned problems regarding fluid containing debris flowing
through a choke valve, providing a risk for choke malfunction and
blockage, and the different features required in different phases of the
production in a subsea installation.
[0008] The objects of this invention are obtained as defined in the
appended claim 1.
[0009] Advantageous embodiments are obtained by the features defined in
the appended dependent claims.
[0010] The objectives set forth above are achieved by providing, in a
first aspect of the present invention, Hydrocarbon production system,
comprising a subsea production module, operatively connected to a subsea
well, a subsea receiving module and a main flow path, including a subsea
production choke valve fluidly connecting the production module and the
receiving module, wherein bypass line is arranged parallel to the choke
valve and being connected to the main flow path by a bypass connection,
to conduct production fluid around the choke valve.
[0011] This prevents blockage and malfunction of the choke valve, and
consequently the need for replacement of damaged chokes that could easily
happen if the fluid was transmitted through the choke valve and not the
bypass line. It also removes the problem of changing choke valves
according to amount of fluid flow and production phase.
[0012] In one embodiment the bypass connection comprises at least one
valve capable of opening and closing the access from the main flow path
to the bypass. This is a simple embodiment where the main flow path is
always open, while the bypass can be closed or open. The fluid will flow
the easiest way, which is through the bypass when this is open.
[0013] In another embodiment the valve is a two-way valve that has a first
position to open access to the choke valve and closing access to the
bypass, and a second position to open access to the bypass and close
access to the choke valve. This will close the access to the choke valve
when the bypass is open, thereby eliminating any risk for debris to find
its way to the choke valve.
[0014] In yet another embodiment the valve is a three-way valve that has a
first position to open access to the choke valve and closing access to
the bypass, a second position to open access to the bypass and close
access to the choke valve, and a third position to close access to both
the choke valve and the bypass. This embodiment will enable access to
both the choke valve and the bypass. In this embodiment it is possible to
use the valve to shut the well down when maintenance is being performed
on equipment downstream of the valve.
[0015] In yet another embodiment the valve is a four-way valve that has a
first position to open access to the choke valve and closing access to
the bypass, a second position to open access to the bypass and close
access to the choke valve, a third position to close access to both the
choke valve and the bypass, and a fourth position to open access to both
the choke valve and the bypass. This may be an advantage as the choke
valve can be set to a fully open position and thereby provide an
increased flow rate than what is possible through the bypass alone.
[0016] In a preferred embodiment the bypass is connected to the main flow
path by two connections, one at either side of the choke valve. It is
thereby possible to remove the choke valve while production takes place
through the bypass.
[0017] In a preferred alternative embodiment of the device according to
the first aspect of the present invention, the receiving module is a
manifold. This enables the adding of more wells to the same manifold.
[0018] In yet an alternative embodiment of the device according to the
first aspect of the present invention, the subsea producing module is a
Xmas Tree.
[0019] In a further alternative embodiment of the device according to the
first aspect of the present invention the bypass connection is arranged
to transmit fluid in both directions of the bypass line to provide both
production and injection of fluid. This leads to that the restrictions on
choke valves regarding reverse fluid flow is no longer an issue.
[0020] In still an alternative embodiment of the device according to the
first aspect of the present invention the fluid comprises debris.
[0021] In a second aspect of the present invention, a method is provided
for performing clean-up of a subsea well and a subsea production module
in a hydrocarbon production system, the subsea production module being
adapted to produce a fluid transmitted through a main flow path including
a choke valve, wherein during clean-up a bypass connection is opened to
direct the produced fluid and/or treatment fluid from the well to a
bypass around the choke valve in order to prevent debris in the flow from
damaging or blocking the choke valve.
[0022] The producing module produces a clean-up fluid comprising debris
during the cleaning up, and the clean-up fluid is transmitted through the
main flow path. A bypass connection directs the clean-up fluid through a
bypass line arranged in parallel to the choke valve to prevent
malfunction and blockage of the choke valve due to the fluid comprising
debris.
[0023] In a third aspect of the invention it relates to a method for
controlling the flow in a hydrocarbon production system comprising a
subsea production module, operatively connected to a subsea well, a
subsea receiving module and a main flow path, including a subsea
production choke valve fluidly connecting the production module and the
receiving module, wherein during a situation with a pressure in the well
higher than the pressure necessary to deliver the desired production flow
rate, the choke valve is choked to limit the flow rate to a desired flow
rate; and that during a situation when a flow rate is desired, which
substantially corresponds to the maximum delivery rate of the well, a
bypass line is opened to direct the flow outside the choke valve. This
makes it possible to merely open the bypass when the pressure in the well
has dropped to a certain level over time. It removes the necessity for
replacing the choke valve with another valve with different properties,
i.e. less restriction. It also makes it possible to open up for full
pressure from the well in situations when it is not necessary to limit
the flow from the well, e.g., if another well with lower pressure
connected to the same manifold is shut down, and the present well can be
allowed to produce at maximum without interfering with other wells.
BRIEF DESCRIPTION OF THE DRAWING
[0024] The invention is described in more detail below with reference to
the accompanying drawing, which illustrates the invention by way of an
example.
[0025] FIG. 1 is a schematic view of the invention.
DETAILED DESCRIPTION OF THE INVENTION
[0026] As seen in FIG. 1, a pipeline 7 has a connection to a Xmas Tree and
a subsea well (commonly denoted by reference numeral 8) in one end, and
the pipeline 7 is connected to a manifold 9 at the other end. A choke
valve 3 for controlling the flow through the pipeline 7 is connected
between the two end points 8, 9 of the line 7. For illustration purposes
only, typical building blocks are also shown in FIG. 1. Such building
blocks can be a flow meter 4, sand sensor 5 and injection line 6.
Pressure and temperature sensors PP, PT are also inserted in the pipeline
7. In regular operation of the system seen in FIG. 1, fluid from the
subsea well flows from the Xmas tree 8 through the choke valve 3 to the
manifold 9. During a clean-up process of the subsea well or Xmas Tree 8
the choke valve 3 can not safely handle the debris in the fluid. Thus a
bypass line 2 is implemented as an additional line 2, in parallel with
the choke valve 3 to prevent the choke valve 3 from being damaged by
debris. The bypass line 2 is connected to the pipeline 7 by a bypass
connection 1. The bypass connection 1 has a control function that directs
the flow into the bypass line 2 or through the coke valve 3 according to
the performed operation. During a clean-up process, the process product
which often contains debris will flow through the bypass line 2 instead
of the choke valve 3 (as in the current prior art), i.e. the debris will
not be in contact with the choke valve 3 during the clean-up process, and
the system will be able to perform well clean-up through the Xmas Tree in
a much safer way than in known prior art techniques. By this, a potential
failure of the choke valve 3 will be eliminated, and consequently a
complex and costly process of changing and repairing a damaged choke
valve 3 is avoided. A bypass line 2 will typically be made of the same
material as the pipeline 7, or integrated into the connector block which
bridges the Xmas Tree 8 to the manifold 9. The bypass line 2 is
preferably mounted in the subsea installation at the same time as the
other components of the installation.
[0027] In addition to using the bypass line 2 for transmission of clean-up
products, the bypass line 2 has a function especially for high rate
production periods. In a subsea well the production periods can be high
or low rate. In high rate production periods it will be preferable to
provide flow of as much fluid as possible in the pipeline 7. Without the
bypass line 2, the fluid will flow through the choke valve 3, which will
give a large pressure drop over the choke valve 3 and will not provide
maximum flow. This will happen even if the choke valve is fully open. By
letting the fluid flow through the bypass line 2 in high rate production
periods, the pressure drop over the bypass line 2 will be minimal
compared to the choke valve 3, and maximum flow can be provided. Thus,
the oil recovery can be increased during high rate production periods.
[0028] The bypass line 2 also provides good controllability of the choke
valve 3 during the first phases at the same time as it provides a maximum
flow in later phases of the production in the well, without the need of
replacing the choke valve 3 with another choke valve 3 with different
features. The bypass line 2 provides a neglectable pressure drop over the
choke valve 3, and thus the Xmas Tree can operate with higher production
rates than the choke valve 3 is designed for.
[0029] Another additional function of the bypass line 2 is that it can be
arranged to transmit fluid in both directions, to and from the Xmas Tree.
In this way, the same Xmas Tree can be used for both production and
injection. Reverse flow of the fluid (injection) through a choke valve 3
has many restrictions, and will require a higher injection pressure to
overcome the pressure drop over the choke valve, but by using the bypass
line 3 these restrictions are no longer an issue.
[0030] Summarized, by providing a bypass line 2 in parallel with a choke
valve 3 the present invention might add a good cost saver regarding
increased oil recovery, installation cost and any
re-installations/work-over operations could be reduced. The vulnerability
and risk of malfunction of a choke valve 3 is reduced significantly
during a clean-up period.
* * * * *